Answer :
Answer:
Estimated Duration
Explanation:
A PERT Chart is a tool in Project Management that gives a graphical portrayal of an undertaking's timetable. The Program Evaluation Review Technique abbreviated as PERT separates the individual assignments of a venture for investigation.
The most widely recognized components utilized in a PERT chart are:
- Span time.
- Activity
- Early finish time.
- Early Ending time
- Late initiation time.
- Late completion time.
- Critical path
- Slack.
It does not include the Estimated span of time.