Answer :
Answer:
1,370.85 Unfavorable
Explanation:
Standard rate :
= Budgeted variable overhead costs ÷ Budgeted direct labor hours
= $13500 ÷ 640
Direct labor hours = $21.09 per direct labor hour
Standard time to produce goods :
= Budgeted direct labor hours ÷ Production volume
= 640 ÷ 6,400
= 0.10 hours
VOH Efficiency Variance
= ( SH − AH ) × SR
where,
SH are standard direct labor hours allowed
AH are the actual direct labor hours
SR is the standard variable overhead rate
(SH − AH ) × SR
= [(4,200 × 0.10) - 485] × $21.09
= (420 - 485) × $21.09
= 1,370.85 Unfavorable