Answer :
Answer:
The correct answer is A.
Explanation:
Giving the following information:
Actual number of cars detailed 250
Actual direct labor hours used 625
Actual total direct labor cost $6,500
Budgeted number of cars to be detailed 300
Standard direct labor cost per hour $10
Standard direct labor per car 1.5
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (10 - 10.4)*625= $250 unfavorable