Answer :
Answer:
a.
i. $6
ii. $8
b.
i. $600,000
ii. $800,000
Explanation:
a. Standard Cost is the cost which is stated or described as the amount which is per unit.
i. For materials
Standard Cost = Expected amount to be spend on materials / Units
= $600,000 / 100,000
= $6
ii. For labor
Standard Cost = Expected amount to be spend on labor / Units
= $800,000 / 100,000
= $8
b. Budgeted cost are those costs which are stated as the total or aggregate amount.
i. For total material cost
Budgeted cost for the year = Expected or total cost spend on materials
= $600,000
ii. For total labor cost
Budgeted cost for the year = Expected or total cost spend on labor
= $800,000