Answer :
Answer:
$3.75
Explanation:
The computation of the fabrication department overhead rate per machine hour is shown below:
But before that first determine the following calculations
The Total number of hours is
= 1,000 ×6 + 2,000 × 9
= 6,000 + 18,000
= 24,000
And, the total estimated overhead is $90,000
So, the overhead rate per machine hour for the fabrication department is
= $90,000 ÷ 24,000 hours
= $3.75